Back to our work

Other demolition

Shortening an outbuilding

We shortened a timber outbuilding by 1.5 metres, built a new end wall and clad it with the building's old boarding.

Service
Other demolition
The shortened outbuilding next to the tower, with a man working on the roof and demolished timber parts in front
The road-facing side of the timber outbuilding, with two grey doors, before shortening

The road-facing side of the timber outbuilding, with two grey doors, before shortening

1 / 5

About the job

What was done?

The timber outbuilding had vertical boarding and a sheet metal roof. It stood next to a wooden tower with a metal spiral staircase. We shortened the building by 1.5 metres and removed the walls, roof and downpipe from that section. At the shortened end of the building, we built a new wall and clad it with the old boarding from the demolished section, so the wall matches the rest of the facade. A concrete slab was uncovered under the demolished section.

Work stages

How did it go?

  1. 01

    Demolishing the end of the building

    We removed the wall boarding and roof from a 1.5-metre section at the end of the building. We also took down the downpipe.

  2. 02

    Building the new wall

    We built a new end wall for the shortened building.

  3. 03

    Cladding the wall with boarding

    We clad the new wall with the old boarding from the demolished section so that it matches the rest of the facade.

Get in touch

Let’s talk about your project.

Describe the job and where the site is. Add photos if you can.

+372 5663 5298
  • Clear quote
  • Agreed schedule
  • Removal and clean-up as needed
Call