Back to our work

Interior demolition

Bathroom pod and floor demolition

In Klooga, we demolished a bathroom pod in an apartment, took up the floors and carried the furniture out.

Location
Klooga
Hallway after demolition: wardrobe carried out, floor coverings removed, front door left in place
Hallway before the work: large wardrobe, wooden floor and front door
BEFOREAFTER
Hallway before the work: large wardrobe, wooden floor and front door

Hallway before the work: large wardrobe, wooden floor and front door

1 / 7

About the job

What was done?

Before the work, the apartment had a separate WC and bathroom. The bathroom had a green bath and patterned wall tiles, and the floor had mosaic-patterned linoleum. The kitchen had kitchen units, an electric cooker, a sink and white wall tiles, and the hallway had a wooden floor and a large wardrobe. We demolished the bathroom pod, took up the floor coverings and carried the furniture out of the apartment. After the work, the rooms were empty and the floors were stripped back to the concrete. In the kitchen, the window and radiator were left in place.

Work stages

How did it go?

  1. 01

    Removing the furniture

    We carried the hallway wardrobe and the kitchen units, together with the cooker and sink, out of the apartment.

  2. 02

    Bathroom pod demolition

    We demolished the WC and bathroom pod together with its fixtures.

  3. 03

    Removing the floors

    We took up the linoleum and the wooden floor in the hallway, leaving the concrete floor exposed.

Get in touch

Let’s talk about your project.

Describe the job and where the site is. Add photos if you can.

+372 5663 5298
  • Clear quote
  • Agreed schedule
  • Removal and clean-up as needed
Call